Gold Mine Processing Plant

GBI was initially contracted by Oceana Gold to provide 18 process tanks for a new processing plant at their Haile Gold mine located in South Carolina.  M3 Engineering was assisting Oceana as advising engineer.

Once on site, GBI's crews were immediately recognized by Oceana and M3 for their excellent safety, quality and work ethic. With a tight timeline and schedule to meet, GBI was able to take over additional contractual responsibilities and ultimately complete all of the following scope in under 9 months. 

  • 18 process tanks of various sizes
  • Full exterior/interior coatings
  • 400 tons of structural steel
  • 14 agitators and drives
  • 3 thickeners & mechanisms
  • 8 intermediate screens
  • 4 3-deck shakers
  • 10-ton OH crain & rail
  • 8 carbon advance pumps
  • 3 MCC buildings
  • 8000 feet Victaulic and welded stainless piping
  • Plant pre-commisioning